Online Help Process Modeler
.

Simulation Result

Simulation Result

As a result we get an Excel file including all results and predefined diagrams. Here is an example showing the summary of the most important process indicators and a process time diagram including Cycle Time, Active Time, Resource Wait Time as a function of the process instances (1-100).

figure 16: Summary and Process Times

Another example showing the Activities, Resources, Duration, Resource Utilization and Resource Cost.


figure 17: Duration, Utilization, Cost

Be aware that there are various further statistics, indicators and diagrams possible. The shown example is only a subset and illustrates a fraction of the potential analysis.

Additionally, there is only one simulation scenario shown. You will get more benefit if you take more than one example and compare it with each other. For example the comparison between “actual process” and “target process”.